MGMT627 Assignment 2 Solution July 2010
VU Help • House Banner VU Help Virtual University Students - Assignments, Solved Papers, GDB & Exam Help Student Help Forum • Collaborative • Free Support
#1
Question 1:
Considering a and b
Tell separately in which situation (a or b), either it is-scope creep and if it is then of what type?
Answer:

In a highway project, the Govt. is the customer; the construction of the highway was 190 which were then extended to 5 km more. The government wants to increase the project scope. It means the project manager now has to manage the construction of 195 km highway.
In situation a:
In the situation of a, the resources and time-line has been fixed but the scope of the highway increases with the size increases. The deliverable size of the highway was 190 km before, which was further extended and the additional 5 km was added to the first project but the resources remains fixed.
If there isn’t any increase in budget and schedule time, the project team may flow away from the original goals or objectives, as the capacity of the project increases, the project manager needs more task for completing the project in limited resources and limited time-line, which was designed for the smaller project. Due to this the scope creep became effect in overflow of the project's original goals.
For situation b:
In situation b, the additional project is not bad for the project manager because the government is providing extra funds for additional construction and also provides extra time limit for completing the project. So the situation b is not scope creep because the government is providing more funds to be issued and 8 week additional time for the construction.


Question 2:
How this additional construction will affect the Work Breakdown Structure (WBS) of your project?
Answer:

The work breakdown structure of any project is specially made for networking of the project. It contains all the work associated with the project. It divides the whole work of the project into pieces, so that the project manager can better understand the project. The WBS must be flexible, because the
project’s requirements changes every time, and it must be able to use in every circumstances.

Work Breakdown Structure is not a description of the process which will be following to perform the project, it also doesn’t address the schedule which define how and when the deliverable will be produces, rather it is specifically limited to describe and detailing the project’s outcome or scope.

The additional construction of the highway will slightly affect the Work breakdown structure because the project manager will need to describe and make the detailed diagram for handling the construction process. The changes may occur in the scope of the project because of the additional construction but the project manager should clearly define the changes.
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  SEO in Simple Words: How a VU Student Can Write a Clearer Assignment or Blog Post admin 0 33 11-01-2026, 05:11 AM
Last Post: admin
  Cs403 Assignment 3 Helping material May 8,2010 viki 1 5,266 04-28-2020, 03:19 PM
Last Post: ClaireBeauc
  cs301 assignment no 3 Solution 20 January 2016 Vuhelper 0 11,127 01-20-2016, 03:32 PM
Last Post: Vuhelper
  CS201 Assignment vo 3 Solution 20th January 2016 Vuhelper 2 2,651 01-20-2016, 03:28 PM
Last Post: Vuhelper
  CS101 Assignment no 3 Solution 20th January 2016 Vuhelper 0 2,326 01-20-2016, 03:25 PM
Last Post: Vuhelper
  SOC101 INTRODUCTION TO SOCIOLOGY assignment no 3 Solution 20 January 2016 Vuhelper 0 1,907 01-20-2016, 03:19 PM
Last Post: Vuhelper
  CS402 Assignment No 4 Solution & Discussion Xpert 0 2,142 08-01-2015, 02:33 AM
Last Post: Xpert
  cs101 Assignment No. 1 Solution 21 may spring 2015 semester Xpert 0 2,952 05-21-2015, 12:41 AM
Last Post: Xpert
  Assignment solution eng 301 due date 20 may 2015 rumesa khan 3 4,577 05-20-2015, 01:34 AM
Last Post: Xpert
  PHY301 Circuit Theory Assignment No. 1 idea Solution spring may 2015 semester Xpert 0 1,603 05-15-2015, 03:52 AM
Last Post: Xpert

Forum Jump:


Users browsing this thread: 1 Guest(s)
VU Help • House Banner VU Help Virtual University Students - Assignments, Solved Papers, GDB & Exam Help Student Help Forum • Collaborative • Free Support