cs 507 todays paper subjective part
total 23 questions for 38 marks
16qs x 1 mark=16
3qs x 2 marks=6
qs x 3 marks=6
2qs x 5 marks=10
almost all mcqs from past papers ) cs 507 today's paper subjective part 2 marks questions:
Q1=differentiate between incremental and iterative model?
Q2=give examples of transaction processing system?
Q3=differentiate between two graphic tools used in tqm?
3 marks questions:
Q1=give limitations of incremental model?
Q2=enlist phases of decision making process?
5 marks questions:
Q1= describe information requirement for manufacturing information system at each level?
Q2= suppose you have to build a new house, what phases would you consider according to spiral model?
Posts: 9,583
Threads: 8,089
Joined: Apr 2011
cs 507 todays paper subjective part
total 23 questions for 38 marks
16qs x 1 mark=16
3qs x 2 marks=6
2qs x 3 marks=6
2qs x 5 marks=10
almost all mcqs from past papers ( dua waqar's 20 papers file) must see
cs 507 today's paper subjective part
2 marks questions:
Q1=differentiate between incremental and iterative model?
Q2=give examples of transaction processing system?
Q3=differentiate between two graphic tools used in tqm?
3 marks questions:
Q1=give limitations of incremental model?
Q2=enlist phases of decision making process?
5 marks questions:
Q1= describe information requirement for manufacturing information system at each level?
Q2= suppose you have to build a new house, what phases would you consider according to spiral model?
Posts: 9,583
Threads: 8,089
Joined: Apr 2011
Total Marks =38
Total Question= =23
MCQS = 16
Subjective 2 marks = 3
Subjective 3 marks = 2
Subjective 5 marks = 2
Write the department names of an educational organization (University/) (2)
How would you differentiate the term architechture and information architechture? (2)
What are the task performed by CRM ? (2)
What is the term "iterative" means in Spiral model? (3)
What would be the document of software project which is developed under the
procedural development phase? (3)
The difference between incremental model and iterative model with one exmple? (5)
The benefits of HRIS (Human Resources Information System) of an orgnization (5)
Posts: 9,583
Threads: 8,089
Joined: Apr 2011
Total Marks =38
Total Question= =23
MCQS = 16
Subjective 2 marks = 3
Subjective 3 marks = 2
Subjective 5 marks = 2
Write the department names of an educational organization (University/) (2)
How would you differentiate the term architechture and information architechture? (2)
What are the task performed by CRM ? (2)
What is the term "iterative" means in Spiral model? (3)
What would be the document of software project which is developed under the
procedural development phase? (3)
The difference between incremental model and iterative model with one exmple? (5)
The benefits of HRIS (Human Resources Information System) of an organization (5)
Posts: 9,583
Threads: 8,089
Joined: Apr 2011
today paper CS507
Q1. Wat is scope creep?????
Q2. Data mining example other than handout..
Q3. Subsystems of Manufacturing Information system.
Q4. objectives of system.
Q5. Limitations of spiral model.
Posts: 9,583
Threads: 8,089
Joined: Apr 2011
Mostly MCQ from past papers
Subjective:
Differentiate between any basic tools used in Total Quality Management 02Marks
What are the basic issues that should be considered at the beginning of system planning 02Marks?
Identify any two procedure used in accounting information system 02 Marks
List any three narrative module of choice phase of decision making 03
Marks
Do you agree that Fuzzy Logic is always difficult to manage .If yes Justify your answer 03 Marks
What information requirement foe manufacturing information system at each level 05 Marks
What is Scope creep .which Model Led to it and how. 05 Marks