a. Vendor 1
b. Vendor 2
c. Vendor 3
d. Vendor 4
e. We need to compute the following for all the vendors - (0.4*Price + 0.6*Quality). The scores come out to be vendor 1 - 10.4, vendor 2 - 10, vendor 3 - 9.6, and vendor 4's 11. Since vendor 4 has the highest score, it should get selected.
• You are the Project Manager for XYZ project. The scope of the project has been completed. You receive a request for a new module to be developed as part of this project. What should you do next?
a. You should approach the Project sponsor and ask her for a new module to be developed as part of this project.
b. You should approach the Senior Management and ask them for a new module to be developed as part of this project.
c. You should send the request to Change Control Board for approval.
d. Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.
Answer:
d. As the scope is completed, the project is complete. Additional work should be done as part of a new project.