11-27-2014, 04:05 PM
in Q 1
activity 1-3-4-6-7 is valid
and its duration is = 51
nd 2nd question
put the formula
a+4m+b/6 in each job
and calculate final duration by summing up all
activity 1-3-4-6-7 is valid
and its duration is = 51
nd 2nd question
put the formula
a+4m+b/6 in each job
and calculate final duration by summing up all