1.5.3 The Backward Pass - Latest Finish Time Rule
To make the Backward Pass, we begin at the sink or the final event and work backwards to the first event.
[ATTACH=CONFIG]24183[/ATTACH]
At Event 3 there is only one activity, Activity 3-4 in the backward pass, and we find that the value is 11-7 = 4 weeks. However at Event 2 we have to evaluate 2 activities, 2-3 and 2-4. We find that the backward pass through 2-4 gives us a value of 11-6 = 5 while 2-3 gives us 4-0 = 4. We take the smaller value of 4 on the backward pass.
To make the Backward Pass, we begin at the sink or the final event and work backwards to the first event.
[ATTACH=CONFIG]24183[/ATTACH]
At Event 3 there is only one activity, Activity 3-4 in the backward pass, and we find that the value is 11-7 = 4 weeks. However at Event 2 we have to evaluate 2 activities, 2-3 and 2-4. We find that the backward pass through 2-4 gives us a value of 11-6 = 5 while 2-3 gives us 4-0 = 4. We take the smaller value of 4 on the backward pass.
0300-9520262
Get solution in 24 hour |cpmputer & internet
mileys81:[SIZE="4"][SIZE="3"]....[/SIZE][/SIZE]