List down the tasks of Initializing process (2)
Requirement gathering:
Scope determination:
[FONT=&quot]Resource allocation[/FONT]:[FONT=&quot][/FONT]
[FONT=&quot]Initial project plan:[/FONT][FONT=&quot][/FONT]


What is prototype (2)
When a software engineer is provided incorrect, incomplete requirements, which areas are affected most (3)
Name any six planning process tasks (3)
[FONT=&quot]Scope Planning[/FONT]
[FONT=&quot]2. Scope Definition[/FONT]
[FONT=&quot]3. Activity Definition[/FONT]
[FONT=&quot]4. Activity Sequencing[/FONT]
[FONT=&quot]5. Activity Duration Estimating[/FONT]
[FONT=&quot]6. Resource Planning[/FONT]
[FONT=&quot]7. Cost Estimating[/FONT]
[FONT=&quot]8. Cost Budgeting Risk Planning[/FONT]
[FONT=&quot]9. Schedule Development[/FONT]
[FONT=&quot]10. Quality Planning[/FONT]
[FONT=&quot]11. Communications Planning[/FONT]
[FONT=&quot]12. Organization Planning[/FONT]
[FONT=&quot]13. Staff Acquisition[/FONT]
[FONT=&quot]14. Procurement Planning[/FONT]
[FONT=&quot]15. Project Plan Development[/FONT][FONT=&quot][/FONT]

Describe Formal change process in detail (5)
A request for change triggers that change control procedure. Then request is logged in the change request register. Next, the change request number is recorded in the change request evaluation plan. The request is evaluated and analyzed to check if the change is valid. Change request is also evaluated in terms of the number of items affected and the effort involved in effecting the change. Finally, the possible outcome of the change request is communicated. The request for change is rejected, deferred, or approved. If the request for change is rejected, the requestor needs to log a fresh request. A deferred change request is evaluated at a later date while the change request that is approved is implemented.

Discuss technology related problems in a software project (5)


1 ) Define the SAFETY RISKS AND HAZARDS 5 Marks
2 ) Define the importance Human rourcs management in the terms of the Software Mangemet ?
3 Deinf the Risk & Change Management Concepts
4 Explain the WBS ?
5 Define the disadvantages of the SLOC?
6 Define the Project scheduling ?
7 Define the SQA Concept?
8 Write the Over view about RISK REFINEMENT?
9 Drwa the Product Orident table According to the WBS?
10 Deind the Product risk ? 5 makrks


Another Paper:-

Total 40 Question
30 MCQs of (Marks 1)
31 - Explain estimation? 2 Marks
32- Explain WBS ? 2 Marks
33- Explain Quality Control 2 Marks
34- Risk and management 2 Marks
35 what is COOMO ? 3 Marks

The COCOMO technique is another popular estimation technique. Dr: Barry
Boehm propounded this technique in 1981. COCOMO uses cost driver attributes
to calculate the effort and duration of a project. The COCOMO technique has
three levels of implementation. With each level, the complexity of the model
increases. The levels of the COCOMO technique are:
i. Basic
ii. Intermediate
iii. Advanced

36 Explain SLOC ? 3 Marks
37 explain Project Scheduling ? 3 Marks
38 RISK REFINEMENT ? Marks 3
39 what is Quality Assurance explain Marks 5
40 what is RISK PROJECTION Marks 5



CS615 Software Project Management Final Paper Spring 2010
30 MCQz
Q no. 31 List the names of inputs to team development. Marks: 2
Q no. 32 What are the software risk components. Marks: 2
Q no. 33 What is meant by constraints and what types of constraints are added to the tasks of MS Project? Marks: 2
Q no. 34 What acts as a bridges between software engineering and software design? Marks: 2
Q no. 35 Write names of six methods of requirements elicitation for software? Marks: 3

[FONT=&quot]1. Initiating the Process[/FONT][FONT=&quot][/FONT]
[FONT=&quot]2. Facilitated Application Specification Techniques[/FONT][FONT=&quot][/FONT]
[FONT=&quot]3. Quality Function Deployment[/FONT][FONT=&quot][/FONT]
[FONT=&quot]4. Use Cases[/FONT][FONT=&quot][/FONT]
[FONT=&quot]5. Analysis Principles[/FONT][FONT=&quot][/FONT]
[FONT=&quot]6. Software Prototyping[/FONT][FONT=&quot][/FONT]

Q no. 36 As a project manager, how will you deal with risks in projects? Marks: 3
Q no. 37 What are outputs that come from staff acquisition? Marks: 3

[FONT=&quot]Outputs from Staff Acquisition[/FONT]
[FONT=&quot]i. Project staff assigned[/FONT][FONT=&quot]. [/FONT]The project is staffed when appropriate people have been
reliably assigned to work on it. Staff may be assigned full time, part time, or
variably, based on the needs of the project.
[FONT=&quot]ii. Project team directory[/FONT][FONT=&quot]. [/FONT]A project team directory lists all the project team
members and other stakeholders. The directory may be formal or informal, highly
detailed or broadly framed, based on the needs of the project.[FONT=&quot][/FONT]

Q no. 38 How will you explain the concept of tracking the project plan? Marks: 5
Q no. 39 What is functional decomposition? Elaborate it with the perspective of WBS. Marks: 5
Q no. 40 Discuss the concept of quality. Elaborate it with respect to what, who, why, and what are the steps for quality. Marks: 5



Question No: 1 ( Marks: 15 )


a) How does intermediate COCOMO differ from Basic COCOMO? Give at least two differences. (6)
b) Explain why software quality assurance organization should be independent of the development organization. (9)


Question No: 2 ( Marks: 18 )

Assume that you are the newly appointed Software Project Manager at “EWork”, an American Software Company based in Boston. The staff that has been allocated to work for you consists of two analyst/programmers sufficiently versed in the state-of-the-art programming languages and associated technology. You are also informed about a policy at EWork that has a maximum monthly salary of US $. 20000 for the analyst/programmer employee grade.
a) List the roles of a Software Project Manager. What are the skills which a software project manager needs to have in the job? In your opinion, do you think that it will help software project managers to update their knowledge with respect to latest technologies? What are your immediate tasks as the Software Project Manager at EWork?(12)
b) Give the steps which you would follow to make a cost proposal for the project. (6)


Question No: 3 ( Marks: 16 )

a) Using yours knowledge of ‘Work Breakdown Structures’, answer the following: (6)
§ How much detailed should a WBS be for an online banking system?
§ What tools are available for creating WBS?
b) What three knowledge areas comprise the triple constraint of project management? Explain your answer. (10)


Question No: 4 ( Marks: 2 ) - Please choose one

Cost, effort, risks, and resources are the factors included in--------

►
Estimation

►
Testing

►
Development

►
Maintenance



Question No: 5 ( Marks: 2 ) - Please choose one

Extent to which the program can be used in more than one program or system is called -------

►
Portability

►
Reusability

►
Interoperability

►
Configurability



Question No: 6 ( Marks: 2 ) - Please choose one

The nature of software applications can be characterized by their information

►
complexity

►
content

►
determinacy

►
content and determinacy



Question No: 7 ( Marks: 2 ) - Please choose one

The software quality assurance activity which is performed to check errors in logic, function, or implementation for any representation of the software is called :

►
Inspection

►
Formal technical review(s)

►
Walkthrough

►
Auditing



Question No: 8 ( Marks: 2 ) - Please choose one

Which of the items listed below is not one of the software engineering layers?

►
Process

►
Manufacturing

►
Methods

►
Tools



Question No: 9 ( Marks: 2 ) - Please choose one

The first step in project planning is to --------------------

►
Determine the budget

►
Select a team organizational model

►
Determine the project constraints

►
Establish the objectives and scope



Question No: 10 ( Marks: 2 ) - Please choose one

The requirements phase precedes the design phase

►
True

►
False



Question No: 11 ( Marks: 2 ) - Please choose one

Software engineers do not need to consider hardware when designing a computer-based system

►
True

►
False


Attached Files
.doc   cs615.doc (Size: 34 KB / Downloads: 226)
.doc   CS615 Papers.doc (Size: 131 KB / Downloads: 384)
Reply


Messages In This Thread
cs615 fall 2010 subjective paper held on 19-02-2011 - by Xpert - 02-20-2011, 12:21 AM

Possibly Related Threads…
Thread Author Replies Views Last Post
  Final Term Current Paper MKT501 Marketing Management 12 August 2010 viki 1 3,469 08-20-2020, 08:12 PM
Last Post: Johnnieaunders
  All Current Finalterm Papers Solved & Unsolved Held On 10 August 2010 viki 18 11,980 05-14-2012, 02:24 AM
Last Post: malik zani
  All Current Finalterm Papers Solved & Unsolved Held On 7 & 8 August 2010 viki 4 5,550 01-22-2012, 10:14 PM
Last Post: malika malik
  Final Term Current Paper CS101 Introduction to Computing 12 August 2010 viki 3 4,210 01-03-2012, 05:20 PM
Last Post: Muhammad Shahid hiraj
  Sta301 current paper 14 feb 2011 for fall 2010 Xpert 5 5,401 11-21-2011, 04:21 PM
Last Post: mahira
  Final Term Paper Current MTH101- Calculus And Analytical Geometry 10 August 2010 viki 6 6,501 11-03-2011, 10:59 PM
Last Post: rabeel
  mkt610 paper 18-7-2011 nisreenjodhpur 0 3,764 07-19-2011, 01:39 AM
Last Post: nisreenjodhpur
  Final Term Current CS401 Computer Architecture and Assembly Language 10 August 2010 viki 2 4,221 07-07-2011, 11:28 PM
Last Post: Xpert
  CS401 Final Paper kazim 1 3,240 06-09-2011, 02:47 AM
Last Post: sumaira kharal
  cs504 8 december fall 2010 Midterm paper Subjective Xpert 2 3,210 05-16-2011, 05:00 AM
Last Post: Xpert

Forum Jump:


Users browsing this thread: 1 Guest(s)
VU Help • House Banner VU Help Virtual University Students - Assignments, Solved Papers, GDB & Exam Help Student Help Forum • Collaborative • Free Support